General
Concrete Information  |
|
|
|
|
Problems/Troubleshooting Concrete  |
|
|
|
|
 |
JOBSITE ADDITION OF WATER
What is Jobsite
Addition of Water?
Jobsite addition of water is the addition of water to ready
mixed concrete in a truck mixer after arrival at the location of
the concrete placement. Such tempering of concrete may be done
with a portion of the design mixing water which was held back
during the initial mixing, or with water in excess of the design
mixing water, at the request of the purchaser.
Why is Water Added at the Jobsite?
When concrete arrives at the jobsite with a slump that is
lower than that allowed by design or specification and/or is of
such consistency so as to adversely affect the placability of
the concrete, water can be added to the concrete to bring the
slump up to an acceptable or specified level. This can be done
when the truck arrives on the jobsite as long as the specified
slump and/or water-cement ratio is not exceeded. Such addition
of water is in accordance with ASTM C 94, Standard
Specification for Ready Mixed Concrete.
The ready mixed concrete supplier designs the concrete mixture
according to industry standards to provide the intended
performance. Addition of water in excess of the design mixing
water will affect concrete properties, such as reducing strength
and increasing its susceptibility to cracking. If the purchaser
requests additional water, in excess of the design mix, the
purchaser assumes responsibility for the resulting concrete
quality. The alternative of using a water reducing admixture or
super-placticizer to increase concrete slump should be
considered. Provided segregation is avoided, increasing the
slump of concrete using admixtures usually will not
significantly alter concrete properties.
How To Add
Water at the Jobsite
-
The maximum
allowable slump of the concrete must be specified or determined
from the specified nominal slump plus tolerances.
-
Prior to
discharging concrete on the job, the actual slump of the
concrete must be estimated or determined. If the slump of the
concrete is measured, it should be on a sample from the first
1/4 cubic yard (0.2 meters cubed) of discharged concrete and the
result used as an indicator of concrete consistency and not an
acceptance test. Tests for acceptance of concrete should be made
in accordance with ASTM C 172.
-
At the jobsite,
water should be added to the entire batch so that the volume of
concrete being retempered is known. A rule of thumb that works
reasonably well is-1 gallon, or roughly 10 lb., of water per
cubic yard for 1 inch increase in slump (5 liters, or 5 kg, of
water per cubic meter for 25 mm increase in slump).
-
All water added to
the concrete on the jobsite must be measured and recorded.
-
ASTM C 94 requires
an additional 30 revolutions of the mixer drum at mixing speed
after the addition of water. In fact, 10 revolutions will be
sufficient if the truck is able to mix at 20 revolutions per
minute (rpm) or faster.
-
The amount of water
added should be controlled so that the maximum slump and/or
water-cement ratio, as indicated in the specification, is not
exceeded. After more than a small portion of the concrete is
discharged no water addition is permitted.
Upon obtaining the desired slump and/or maximum water-cement
ratio no further addition of water on the jobsite is permitted.
-
A pre-concreting
conference should be held to establish proper procedures to be
followed, to determine who is authorized to request a water
addition, and to define the method to be used for documentation
of water added at the jobsite.
ASTM C 94
Jobsite Water Addition
-
Establish the
maximum allowable slump and water content permitted by the job
specification.
-
Estimate or
determine the concrete slump from the first portion of concrete
discharged from the truck.
-
Add an amount of
water such that the maximum slump or water-cement ratio
according to the specification is not exceeded.
-
Measure and record
the amount of water added. Water in excess of that permitted
above should be authorized by a designated representative
of the purchaser.
-
Mix the concrete
for 30 revolutions of the mixer drum at mixing speed.
Do not add
water if:
- The maximum
water-cement ratio is reached,
- The maximum
slump is obtained, or
- More than 1/4
cubic yard (0.2 meters cubed) has been discharged from the
mixer.
[back]
GENERAL INFORMATION REGARDING CONCRETE -
ADMIXTURES
-
Air-entraining admixtures are liquid chemicals added during
batching concrete to produce microscopic air bubbles, called
entrained air, when concrete is mixed. These air bubbles improve
the concretes resistance to damage caused by freezing and
thawing and deicing salt application. In plastic concrete
entrained air improves workability and may reduce bleeding and
segregation of concrete mixtures. For exterior flatwork (parking
lots, driveways, sidewalks, pool decks, patios) that is
subjected to freezing and thawing weather cycles, or in areas
where deicer salts are used, specify a normal air content of 4%
to 7% of the concrete volume depending on the size of coarse
aggregate. Air entrainment is not necessary for interior
structural concrete since it is not subjected to freezing and
thawing. It should be avoided for concrete flatwork that will
have a smooth troweled finish. In high cement content concretes,
entrained air will reduce strength by about 5% for each 1% of
air added; but in low cement content concretes, adding air has
less effect and may even cause a modest increased strength due
to the reduced water demand for required slump.
-
Water Reducers are used for two different purposes; to lower the
water content in plastic concrete and increase its strength or
to obtain higher slump without adding water. Water-reducers will
generally reduce the required water content of a concrete
mixture for a given slump. These admixtures disperse the cement
particles in concrete and make more efficient use of cement.
This increases strength or allows the cement content to be
reduced while maintaining the same strength. Water-reducers are
used to increase the slump of concrete without adding water and
are useful for pumping concrete and in hot weather to offset the
increased water demand. Some water-reducers may aggravate the
rate of slump loss with time. Mid-range water reducers are
now commonly used and they have a greater ability to reduce the
water content. These admixtures are popular as they improve the
finishability of concrete flatwork.
-
Retarders are chemicals that delay the initial setting time of
concrete by an hour or more. Retarders are often used in hot
weather to counter the rapid setting caused by high
temperatures. For large jobs, or in hot weather, specify
concrete with retarder to allow more time for placing and
finishing. Most retarders also function as water reducers.
-
Accelerators reduce the initial set time of concrete and give
higher early strength. Accelerators do not act as an antifreeze;
rather, they speed up the setting and rate of strength gain,
thereby making concrete stronger to resist damage from freezing
in cold weather. Accelerators are also used in fast track
construction requiring early form removal, opening to traffic or
load application on structures. There are two kinds of
accelerating admixtures: chloride based and non-chloride based.
One of the more effective and economical accelerators is calcium
chloride, which is available in liquid or flake form. For
non-reinforced concrete, calcium chloride can be used to a limit
of 2% by the weight of the cement. Because of concerns with
corrosion of reinforcing steel induced by chloride, lower limits
on chlorides apply to reinforced concrete. Prestressed concrete
and concrete with embedded aluminum or galvanized metal should
not contain any chloride-based materials because of the
increased potential for corrosion of the embedded metal.
Non-chloride based accelerators are used where there is concern
of corrosion of embedded metals or reinforcement in concrete.
-
High Range Water Reducers (HRWR) is a special class of
water-reducer. Often called superplasticizers, HRWRs reduce the
water content of a given concrete mixture from 12 to 25%. HRWR
are therefore used to increase strength and reduce permeability
of concrete by reducing the water content in the mixture; or to
greatly increase the slump to produce “flowing” concrete without
adding water. These admixtures are essential for high strength
and high performance concrete mixtures that contain higher
contents of cementitious materials and mixtures containing
silica fume. For example, adding a normal dosage of HRWR to a
concrete with a slump of 3 to 4 inches (75 to 100 mm) will
produce a concrete with a slump of about 8 inches (200 mm). Some
HRWRs may cause a higher rate of slump loss with time and
concrete may revert to its original slump in 30 to 45 minutes.
In some cases, HRWRs may be added at the jobsite in a controlled
manner.
-
Besides these standard types of admixtures, there are products
available for enhancing concrete properties for a wide variety
of applications. Some of these products include: Corrosion
inhibitors, shrinkage reducing admixtures, anti-washout
admixtures, hydration stabilizing or extended set retarding
admixtures, admixtures to reduce potential for alkali aggregate
reactivity, pumping aids, damp-proofing admixtures and a variety
of colors and products that enhance the aesthetics of concrete.
Contact your local ready mixed concrete producer for more
information on specialty admixture products and the benefits
they provide to concrete properties.
[back]
BLEEDING
Bleeding or bleed water or
water gain is the rising of water to the surface of freshly
placed concrete. Finishing bleed water back into the top layer
of concrete is probably responsible for most surface problems
which is where the best concrete is needed. Wait until the bleed
water evaporates or drag a rubber hose slowly over the entire
surface when concrete is stiff enough that only water will be
removed.
Air-entrained cement and a low slump concrete (stiff) will bleed
very little. Lean mixes, that is low cement content will bleed more.
In winter it is recommended to use heated concrete to reduce
bleeding. This is done by preheating the water.
[back]
CURING IN-PLACE CONCRETE
What
is Curing?
-
Curing is the
maintaining of a satisfactory moisture content and temperature
in concrete. Curing begins after placement and finishing so that
the concrete may develop the desired strength and hardness.
-
Without an adequate
supply of moisture, the portland cement in the concrete cannot
react to form a quality product. Drying may remove the water
needed for this chemical reaction called "hydration" and the
concrete will be weak. Temperature is an important factor in
proper curing, since the rate of hydration is temperature
dependent. For exposed concrete, relative humidity and wind
conditions are also important; they contribute to the rate of
moisture loss from the concrete.
Why Cure? – Several
important reasons . . .
-
Predictable
strength gain. Laboratory tests show that concrete in a dry
environment can lose as much as 50 percent of its potential
strength compared to similar concrete that is moist cured.
Concrete placed under high temperature conditions will gain
early strength quickly but later strengths may be reduced.
Concrete placed in cold weather will take longer to gain
strength, delaying form removal and subsequent construction
-
Improved
durability, especially of non-air-entrained concrete slabs that
may be subjected to freezing conditions during construction.
Well cured concrete has better surface hardness and therefore is
more watertight
-
Better
serviceability and appearance. A concrete slab that has been
allowed to dry out too early will have a soft surface with poor
resistance to wear and abrasion. Proper curing reduces crazing,
dusting, and scaling.
How
To Cure
Systems to keep concrete wet include:
-
Burlap or cotton
mats and rugs used with a soaker hose or sprinkler. Care must be
taken not to let the coverings dry out and adsorb water from the
concrete. The edges should be lapped and the materials weighted
down so that they are not blown away.
-
Straw that is
sprinkled with water regularly. Straw can easily blow away, and
if it dries, can catch fire. The layer of straw should be 6
inches thick, and should be covered with a tarp.
-
Sprinkling on a
continuous basis is suitable provided the air temperature is
well above freezing. The concrete should not be allowed to dry
out between soakings, since alternate wetting and drying may
damage the concrete.
-
Ponding of water on
a slab is an excellent method of curing. The water should not be
more than 20 degrees F cooler than the concrete and the dike
around the pond must be secure against leaks.
-
Damp earth, sand,
or sawdust will cure flatwork, especially floors. There should
be no organic or iron staining contaminants in the materials
used.
Sealing materials include:
-
Liquid
membrane-forming compounds-must conform to ASTM Specifications
at the rate of application that is specified. Apply to the
concrete surface about one hour after finishing. Do not apply to
concrete that is still bleeding, or has a visible water sheen on
the surface. While a clear liquid may be used, a white pigment
will give reflective properties, and allow for inspection of
coverage. A single coat may be adequate, but where possible a
second coat, applied at right angles to the first, is desirable
for even coverage. If the concrete will be painted, or covered
with vinyl or ceramic tile, then a liquid compound that is
non-reactive with the paint or adhesives must be used, or a
compound that is easily brushed or washed off. On floors, the
surface should be protected from the other trades with
scuff-proof paper after the application of the curing compound.
-
Plastic
sheets-either clear, white (reflective) or pigmented. Plastic
should conform to ASTM Standards, be at least 4 mils thick, and
preferably reinforced with glass fibers. The plastic should be
laid in direct contact with the concrete surface as soon as
possible without marring the surface. The edges of the sheets
should overlap and be fastened with waterproof tape and then
weighted down to prevent the wind from getting under the
plastic. Plastic will make dark streaks wherever a wrinkle
touches the concrete so plastic should not be used on concretes
where appearance is important.
-
Waterproof
paper-used like plastic sheeting, but does not mar the surface.
Should also conform to ASTM Standards.
[back]
CRACKING
Cracks in basement walls
-
Temperature and
drying shrinkage cracks.
With few
exceptions, newly placed concrete has Cast-in-place concrete
basements provide durable, high quality extra living space. At
times when proper construction practices are not used
undesirable cracks occur, such as: the largest volume that it
will ever have. This shrinkage tendency is increased by drying
and/or a drop in temperature and can lead to random cracking if
steps are not taken to control the location of the cracks by
providing control joints.
-
Settlement
cracks.
These occur
from non-uniform support of footings or occasionally from
expansive soils.
-
Other structural
cracks.
In basements
these cracks generally occur during backfilling, particularly
when heavy equipment gets too close to the walls.
-
Cracks due to lack
of joints or improper jointing practices.
-
In concrete
basement walls some cracking is normal.
Most
cracks normally occur because one or more of the following rules of
"good concrete practice" were not followed:
-
Providing uniform
soil support.
-
Using moderate
slump concrete and avoiding addition of water to the concrete
mixture on the job.
-
Observing proper
concrete placement practices.
-
Providing control
joints every 20 to 30 feet. e. Backfilling carefully and, if
possible, waiting until the first floor is in place in cold
weather. (Concrete gains strength at a slower rate in cold
weather.)
Since the performance of concrete basements is affected by climate
conditions, unusual loads, materials quality and workmanship, care
should always be exercised in their design and construction. The
following steps should be followed:
-
Site conditions
and excavation.
Soil
investigation should be thorough enough to insure design and
construction of foundations suited to the building site. The
excavation should be to the level of the bottom of the footing.
The soil or granular fill beneath the entire area of the
basement should be well compacted by rolling, vibrating or
tamping. Footings must bear on undisturbed soil.
-
Formwork and
reinforcement.
All
form-work must be constructed and braced so that it can
withstand the pressure of the concrete. Reinforcement is
effective in controlling shrinkage cracks and is especially
beneficial where uneven side pressures against the walls may be
expected. Observe state and local guidelines for wall thickness
and reinforcement if needed.
-
Joints.
Shrinkage
and temperature cracking of basement walls can be controlled by
means of properly located and formed joints. As a rule of thumb,
in 8 ft. high and 8 inch thick walls, vertical control joints
should be provided at a spacing of about 30 times the wall
thickness. These wait joints can be formed by nailing a 3/4 inch
thick strip of wood, beveled from 3/4 to 1/2 inch in width, to
the inside of both interior and exterior wall forms. After the
removal, the grooves should be caulked with a good quality joint
filler.
-
Concrete.
In general,
use concrete with a moderate slump (up to 5 inches). Avoid
retempering. Concrete with a higher slump may be used providing
the mixture is specifically designed to produce the required
strength without excessive bleeding and/or segregation. In areas
where weathering is severe and where the walls may be exposed to
moisture and freezing temperatures air entrained concrete should
be used.
-
Placement and
curing.
Place
concrete in a continuous operation to avoid cold joints. If
concrete tends to bleed and segregate slump must be reduced and
the concrete placed in the form every 20 or 30 feet around the
perimeter of the wall. Higher slump concretes that do not bleed
or segregate will flow horizontally for long distances and
reduce the number of required points of access to the form.
Provide adequate curing and protection to fresh concrete. It
should not be allowed to freeze in cold weather. Preventive
measures could be taken by completely enclosing the structure
with polyethylene sheets and, if necessary, providing heat.
-
Waterproofing
and drainage.
Spray or
paint the exterior of walls with damp proofing asphal-tic
compound. Provide foundation drainage by installing drain tiles
or plastic pipes around the exterior of the footing, then
covering with clean granular fill to a height of at least 1 foot
prior to backfill. Water should be drained to lower elevations
suitable to receive storm water run off.
-
Backfilling and
final grading.
Backfilling should
be done carefully to avoid damaging the walls. Brace the walls
or, if possible, have first floor in place before backfill. To
drain the surface water away from the basement finish grade
should fall off 1/2 to 1 inch per foot for at least 8 feet to 10
feet away from the foundation.
[back]
FINISHING
Finishing should be done with some experience and knowledge to
avoid many mistakes. Having enough help and the right tools and
equipment is very important. A slope of 1/8 in per foot is
necessary to avoid low spots for good drainage of the slab. The
sub-grade should be damp but not standing with water. It is a
good idea to stretch a string across the outside of the forms at
several locations and check the depth. Lets say you were poring
a slab 20 ft. x 20 ft. x 4 in., that would equal 5 yards of
concrete. The same slab at 5 inches deep would equal 6 ¼ yards
making you short 1 ¼ yards and costing you time and money. A
slump of 3 in. to 5in. is recommended. Screeding or straightedge
operations should start before bleed water appears. A Come-along
is often used in front of a screed to keep the proper depth of
the concrete. A come-along should be used instead of a garden
rake since they can cause segregation. Use of a Darby or bull
float will fill in the voids and eliminate the ridges that was
left by the screeding operation. This should be done before
bleed water appears. Bull floating is usually done at right
angles to the direction the concrete was straight edged. Edging
and jointing are done next only after waiting a period for any
bleed water to evaporate. The joint depth should be at least
¼th.the depth of the slab. After bleed water has evaporated and
the concrete has just started to set, it is time to broom finish
or trowel the surface. Broom finishes are recommended for
outside slabs such as driveways, sidewalks, and patios. This
helps prevent slips and falls during the winter months with snow
and ice. Very smooth troweled finishes are usually used in
garages, basements, factory floors, etc. This can be done by
hand or by machine. All concrete exposed to freezing and all
troweled finished concrete should be at least a six bag concrete
mix. Curing should be done as soon as possible and no traffic
should be permitted for at least 7 days.
[back]
FLOWABLE FILL
What is Flowable Fill?
Flowable fill
is a self-compacting low strength material with a flowable
consistency that is used as an economical fill or backfill
material as an alternative to compacted granular fill. Flowable
fill is not concrete nor is it used to replace concrete. Other
terms used for this material are unshrinkable fill, controlled
density fill, flowable mortar or lean-mix backfill.
In
terms of its flowability, the slump, as measured for concrete,
is generally greater than 8 inches. It is self-leveling material
and can be placed with minimal effort and does not require
vibration or tamping. It hardens into a strong material with
minimal subsidence.
While
the broader definition includes material with compressive
strength less than 1200 psi , most applications use mixtures
with strength less than 300 psi.
Why is Flowable Fill Used?
Flowable
fill is an economical alternative to compacted granular fill
considering the savings in labor costs, equipment and time.
Since it does not need manual compaction, trench width or the
size of excavation is significantly reduced. Placing flowable
fill does not require people to enter an excavation, a
significant safety concern. It is also an excellent solution for
filling inaccessible areas, such as underground tanks, where
compacted fill cannot be placed.
Use of Flowable Fill include:
-
Backfill - sewer
trenches, utility trenches, bridge abutments, conduit
encasement, pile excavations, retaining walls, and road cuts.
-
Structural Fill -
foundation sub-base, subfooting, floor slab base, pavement
bases, and conduit bedding.
-
Other Uses -
abandoned mines, underground storage tanks, wells, abandoned
tunnel shafts and sewers, basements and underground structures,
voids under pavement, erosion control, and thermal insulation
with high air content flowable fill.
Flowability
of flowable fill is
important, so the mixture will flow into place and consolidate
due to its fluidity without vibration or puddling action. The
flowability can be varied to suit the placement requirements of
most applications. Hydrostatic pressure and floatation of pipes
should be considered by appropriate anchorage or by placing in
lifts.
Permeability
of flowable
mixtures can be varied significantly to suit the application.
Most mixtures have permeability similar to or lower than
compacted soil.
Durability -
Flowable fill materials are not designed to resist freezing and
thawing, abrasive or most erosive actions, or aggressive
chemicals. If these properties are required, use a high quality
concrete. Fill materials are usually buried in the ground or
otherwise confined. If flowable fill deteriorates in place it
will continue to act as a granular fill.
Flowable fill can be conveyed by pump, chutes or buckets to its
final location. For efficient pumping, some granular material is
needed in the mixture. Due to its fluid consistency it can flow
long distances from the point of placement.
Flowable fill does not need to be cured like concrete but should
be protected from freezing until it has hardened.
Cautions:
-
Flowable
fill while fluid is a heavy material and during placement will
exert a high fluid pressure against any forms, embankment, or
walls used to contain the fill.
-
Placement of
flowable fill around and under tanks, pipes, or large
containers, such as swimming pools, can cause the container to
float or shift.
-
In-place fluid
flowable fill should be covered or cordoned off for safety
reasons.
[back]
JOINTS
Although concrete expands and contracts with changes in moisture
and temperature the general overall tendency is to shrink and,
therefore, crack. Irregular cracks are unsightly and difficult
to maintain. Joints are simply preplanned cracks.
SOME FORMS OF JOINTS ARE:
-
Control joints.
These joints
are constructed to create planes of weakness so that cracks will
occur at the desired location.
-
Expansion
joints.
They separate
or isolate slabs from other parts of the structure such as
walls, footings, or columns, and driveways and patios from
sidewalks, garage slabs stairs, light poles and other
obstructions. They permit movement of the slab and help minimize
cracking caused when such movements are restrained.
-
Construction
joints.
These are
joints that placed at the end of a day's work. In slabs they may
be designed to permit movement and/or to transfer load. Often in
reinforced concrete a conscious effort is made to clean the
joint and bond the next day's work.
WHY ARE JOINTS CONSTRUCTED?
Concrete cracks cannot be prevented entirely, but they can be
controlled and minimized by properly designed joints, because:
-
Concrete is weak in
tension and , therefore, if its natural tendency to shrink is
restrained, tensile stresses develop and cracks are likely to
occur.
-
At early ages,
before the concrete dries out, most cracking is caused by
temperature changes or by the slight contraction that takes
place as the concrete sets and hardens. Later as the concrete
dries it will shrink further and either additional cracks may
form or preexisting cracks may become wider.
-
Joints provide
relief for the tensile stresses and are less objectionable than
random cracks.
HOW TO CONSTRUCT JOINTS
Joints must be carefully designed and properly constructed if
uncontrolled cracking of concrete flatwork is to be avoided. The
following recommended practices should be observed:
-
The maximum joint
spacing in feet should not exceed 2.5 times the thickness in
inches. For example in an 8 in. slab the joints should be no
further apart than 20 feet.
-
All panels should
be square or nearly so. The length should not exceed 1.5 times
the width. L- shaped panels should be avoided.
-
The joint groove
should have a depth of 1/4 the thickness of the slab, but not
less than one inch. Tooled joints must be run early in the
finishing process and rerun later to assure groove bond has not
occurred.
-
The joints can be
tooled during finishing or sawed with a carborundum blade at an
early age. Sawed joints may not be practical if the concrete is
mad with hard aggregates such as quartz, gravel, or trap rock.
-
Sawing is easier if
coarse aggregates contain materials such as limestone or
sandstone. If the joint edges ravel during sawing it must be
delayed, but if sawing is delayed too long sawing can become
difficult.
-
With abrasive saw
blades sawing is often done at an age of one day or even
earlier.
-
Pre-molded joint
filler, building paper or polyethylene should e used to isolate
slabs from building walls or footings. At least two inches of
sand over the top of a footing will also prevent bond to the
footing.
-
To isolate columns
from slabs, form circular or square openings which will not be
filled until after the floor has hardened. Slab control joints
should interest at the openings for columns. If square openings
are used around columns the square should be turned at 45
degrees to have the control joints intersect at the diagonals of
the square.
-
If the slab
contains wire mesh cut out alternate wires across control
joints. Note that wire mesh will not prevent cracking. Mesh
tends to keep the cracks and joints tightly closed.
-
Construction joints
key the two edges of the slab together either to provide
transfer of loads or to help prevent curling or warping of the
two adjacent edges. Galvanized metal keys are preferred for
interior slabs, however, a beveled 1 by 2 inch strip, nailed to
bulkheads or form boards, can be used in slabs that are at least
5 inches thick to form a key which will resist vertical loads
and movements. Metal dowels can also be used in slabs that will
carry heavy loads. Dowels must be carefully lined up and
parallel or they may induce restraint and cause random cracking
at the end of the dowel.
-
Joints in
industrial floors subject to heavy traffic require special
attention to avoid spalling of joint edges. Such joints should
be filled with a material capable of supporting joint edges.
Manufacturer's recommendations and performance records should be
checked before use.
[back]
MOVEMENTS
Concrete shrinks as it dries and swells as it is wetted. As a
rule, when concrete dries and becomes re-saturated, not more
than two-thirds of the initial drying shrinkage will be
recovered.
Heat
of hydration is the heat concrete generates as it hardens
because of the chemical reaction of the cement and water. Heat
of hydration can be a source of temperature-caused movement. If
the temperature increased in a long slab or wall resting on the
ground, the concrete would extend its length by sliding on the
ground: but on cooling, the friction of the ground could cause
tensile forces high enough to severely crack the concrete.
Deflection of concrete beams and slabs is on of the most common
examples of building movements and its effects are conspicuous.
As floors deflect, The partitions they support may separate from
the ceiling above, cracks may develop in the wall, and doors may
not close properly.
MOVEMENTS DUE TO FOUNDATIONS
Reasons are:
-
They are resting on
or more different types of soil.
-
Sloping sites may
require cutting and filling. The fill must be well compacted so
that the foundation and floor will settle no more there than at
the cut end.
-
When groundwater
levels drop, uneven settlements occur. Fast growing trees are
known to desiccate the soil, causing settlements at one side or
corner. The process may develop over a period of years. d.
Mining subsidence. The ground surface may settle were mining
occurred below.
FROST HEAVE
During construction when shallow footings in the interior of the
building are exposed to subfreezing weather, they can suffer
frost heave.
Adfreeze is the adhesion of freezing ground to a pile, pier, or
wall with subsequent heaving. Placing footings below the depth
of frost penetration does not protect foundations from heaving
unless adfreezing of the soil to the structure exceeds maximum
uplift forces.
CONTROL JOINTS IN WALLS
All
concrete and concrete masonry shrinks and swells upon loss or
gain of moisture. Unsightly cracks can be eliminated by
controlling their location. Control joints should be not more
than 20 feet apart in exterior walls with frequent openings. In
walls without openings they should never be more than 25 feet
and within 10 or 15 feet of a corner if possible. Joint spacing
in any exposed cast-in-place interior walls should be identical
to joint spacing in outside walls.
[back]
SITE
The
site must be a well drained, uniform sub-grade. All organic and
foreign material should be completely removed. Fill material
used should be sand, gravel, or stone. Sub-grades should be damp
but never standing with water and free of frost. If possible
slope the ground away from the slab. Any lines or pipes should
be covered with at least 2 inches of sub-base so there is no
bond with the concrete. When the concrete shrinks and is in
contact with pipes and lines this could cause cracks in the
slab.
[back]
WATER-TIGHT BASEMENTS
General Precautions:
-
To be sure that
uneven settlements will not cause cracks in the walls, the
footings should be of sufficient width and be properly
proportioned to carry their loads in accordance with local
building code requirements. In the absence of a local building
code, general practice for residential basement construction
requires footings to have a depth equal to the thickness of the
foundation wall and a width equal to twice the wall thickness.
Where soil conditions do not provide good bearing it is
desirable to spread the footings over more area and to add steel
reinforcements. No portion of the footings should bear on
freshly filled ground, steps being used where faulty excavation
does not permit the bottoms of the footings to be at one level.
-
Downspouts should
be connected to underground drains or arranged to discharge
water away from the walls. Surface water should be drained away
by proper grading or by use of a sloping concrete gutter.
-
Unless the work is
being done in a section of the country having a dry climate, or
the excavation is made in exceptionally well-drained subsoil, a
line of drain tile should be placed around the building at the
side of the footings. The tile should have a slope of about 1/2
inch in 12 feet and should drain to a suitable outlet. Do not
connect downspouts to this tile. When the proper time in the
building operations arrives to place the drain tiles around the
footings, the side slopes of the excavation generally will have
sloughed off and filled in next to the footing where the tile
should be placed. Under such conditions there may be a tendency
to place the drain tile above the footing on the shelf formed by
the footing and the wall. Tile should always be placed at the
side of the footing. A sloping shoulder of mortar should be
placed on the shelf to keep water from collecting there. Joints
between the tile should be covered with pieces of roofing felt
to prevent sediments filling the tile during backfilling. The
tile should be covered for at least 18 inches with a permeable
fill of coarse gravel or crushed stone.
-
In poorly drained
soils the exterior surface of the basement wall should be given
two continuous coatings of hot bituminous material applied at
right angles to each other over a suitable priming coat,
extending from 6 inches above the ground line down over the top
of the footing. Wall must be surface dry when primer is applied.
Primer should be dry before the hot bituminous material is
applied.
Concrete Masonry Walls:
-
Basement walls of
concrete masonry should meet local building code requirements as
to thickness and strength of units. In the absence of a local
building code use units meeting the ASTM specifications for
quality.
-
A full bed of
mortar should be placed on the footing to receive the first
course of block. Face-shell bedding should be used on all
succeeding courses with full mortar coverage on vertical and
horizontal face shells. Joints should be 3/8 inches thick.
Joints should be firmly compacted, after the mortar has
stiffened, with a rounded tool having a diameter slightly larger
than the thickness of the joint.
[back]
FRESH AND HARDENED MORTAR
DESIRABLE PROPERTIES OF FRESH, PLASTIC MORTAR
-
Good mortar is necessary for good workmanship and proper
structural performance of concrete masonry. Since mortar must
bond masonry units into strong, durable, weather tight
structures, it must have many desirable properties and the
materials must comply with specifications. Desirable properties
or mortar while plastic include workability, water retention,
and a consistent rate of hardening.
Workability
-
This property of
plastic mortar is difficult to define because it is a
combination of a number of interdependent, interrelated
properties. The interrelated mortar properties considered as
having the greatest influence on workability are: consistency,
water retention, setting time, weight, adhesion, and
penetrability.
-
The experienced
mason judges the workability of mortar by the way it adheres to
or slides from his trowel. Mortar of good workability should
spread easily on the concrete masonry unit, cling to vertical
surfaces, extrude readily from joints without dropping or
smearing, and permit easy positioning of the unit without
subsequent shifting due to its weight or the weight of
successive courses. Mortar consistency should change with
weather to help in laying the units. A good workable mix should
be softer in summer than in winter to compensate for water loss.
Water Retention
-
This is the
property of mortar that resists rapid loss of mixing water
(prevents loss of plasticity) to the air on a dry day or to an
absorptive masonry unit. Rapid loss of water causes the mortar
to stiffen quickly, thereby making it practically impossible to
obtain good bond and weather tight joints.
-
Water retention is
an important property and related to workability. A mortar that
has good water retention remains soft and plastic long enough
for the masonry units to be carefully aligned, leveled, plumbed,
and adjusted to proper line without danger of breaking the
intimate contact or bong between the mortar and the units. When
low-absorption units such as split block are in contact with a
mortar having too much water retention, they may float.
Consequently, the water retention of a mortar should be within
tolerable limits.
-
Entrained air,
extremely fine aggregate or cementitious materials, or water
adds workability or plasticity to the mortar and increases its
water retention.
Consistent
Rate
of
Hardening
-
The rate of
hardening of mortar due to hydration (chemical reaction) is the
speed at which it develops resistance to an applied load. Too
rapid hardening may interfere with the use of the mortar by the
mason. Very slow hardening may impede the progress of the work
since the mortar will flow from the completed masonry. During
winter construction, slow hardening may also subject mortar to
early damage from frost action. A well-defined, consistent rate
of hardening assists the mason in laying the masonry units and
in tooling the joints at the same degree of hardness. Uniform
joint color of masonry reflects proper hardening and consistent
tooling times.
-
Hardening is
sometimes confused with a stiffening caused by rapid loss of
water, as in the case of low-water-retention mortars with highly
absorptive units. Also, during very hot, dry weather mortar may
tend to stiffen more rapidly than usual. In this case, the mason
may find it advisable to lay shorter mortar beds and fewer units
in advance of tooling.
DESIRABLE PROPERTIES OF HARDENED MORTAR
Bond
-
The general term
"bond" refers to a specific property that can be subdivided
into: (1) the extent of bond, or the degree of contact of the
mortar with the concrete masonry units; and (2) the tensile bond
strength, or the force required to separate the units. A
chemical and a mechanical bond exist in each category.
-
Good extent of bond
(complete and intimate contact) is important to water tightness
and tensile bond strength. Poor bond at the mortar-to-unit
interface may lead to moisture penetration through the unbound
areas. Good extent of bond is obtained with a workable and
water-retentive mortar, good workmanship, full joints, and
concrete masonry units having a medium initial rate of
absorption (suction).
-
Tensile bond
strength is perhaps the most important property of hardened
mortar. Mortar must develop sufficient bond to withstand the
tensile forces brought about by structural, earth, and wind
loads; shrinkage of concrete masonry units or mortar; and
temperature changes.
[back]
BLISTERS
Blisters are the
result of entrapped air (not to be confused with entrained air)
just below the surface. They are usually 1/4 in to 4 inches in
diameter and only about 1/8 in deep. These bubbles of entrapped
air, form and are trapped under a dense surface skin while
troweling. They usually do not appear until sometime after the
first troweling. When blisters do appear, the second troweling
should be delayed as long as possible. This will give the
entrapped air time to cool and subside.
CAUSES
1.
A cold subgrade will slow the set of the bottom of the concrete.
2. Using a dry shake
3. Using a sticky mix from a high cement content.
4. Vibrating if the slump is over 3 inches.
5. Finishing too early
HOW TO AVOID BLISTERS
1.
Don’t seal surface before bleed water has escaped
2. If using a vibrating straightedge, move it forward as
quickly as possible.
3. Use heated concrete to promote an even setting of the
concrete slab
4. Don’t place slabs directly on plastic.
[back]
COLD WEATHER
Concrete, like other construction materials, contracts and
expands with changes in moisture content and temperature and
deflects depending on load and support conditions. When
provisions for these movements are not made in design and
construction, then cracks can occur. Some forms of common cracks
are:
-
Plastic Shrinkage Cracking
-
Cracks Due to Improper Jointing
-
Cracks Due to Continuous External Restraint (Example-Cast in
place wall restrained along bottom edge of footing)
-
Basement Floor Cracks
-
Cracks from Freezing and Thawing
-
Craze Cracks )
-
Settlement Cracks
Cracks rarely affect structural integrity. Most random
individual cracks look bad and although they permit entrance of
water they do not lead to progressive deterioration. They are
simply unsightly. Closely spaced pattern cracks or D-cracks due
to freezing and thawing are an exception and may lead to
ultimate deterioration.
The
majority of concrete cracks usually occur due to improper design
and construction practices, such as:
-
Omission of isolation and control joints and improper jointing
practices.
-
Improper sub-grade preparation.
-
The
use of high slump concrete or addition of water on the job.
-
Improper finishing.
-
Inadequate or no curing.
All
concrete has a tendency to crack and it is not possible to
consistently produce completely crack-free concrete. However,
cracking can be reduced and controlled if the following basic
safeguards are observed:
-
Sub-grade and
Formwork
All top soil
and soft spots should be removed. Regardless of its type, the
soil beneath the slab should be compacted soil or granular fill,
well compacted by rolling, vibrating or tamping. The slab and,
therefore, the sub-grade should be sloped for proper drainage.
Smooth, level sub-grades help prevent cracking. All formwork
must be constructed and braced so that it can withstand the
pressure of the concrete without movement. Polyethylene vapor
barriers increase bleeding and greatly increase cracking of high
slump concrete. Cover the vapor barrier with 1 to 2 inches of
damp sand to reduce bleeding. Immediately prior to concrete
placement, dampen the sub-grade, formwork, and the
reinforcement.
-
Concrete
In general,
use concrete with a moderate slump (not over 5 inches). Avoid
re-tempering. If higher slump, up to 7 inches, is to be used,
proportions will have to be changed and special mixtures
developed to avoid recessive bleeding, segregation and low
strength. Specify air-entrained concrete for outdoor slabs
subjected to freezing weather.
-
Finishing
DO NOT
perform finishing operations with water present on the surface.
Initial screeding must be promptly followed by bull floating.
For better traction on exterior surfaces use a broom finish. If
evaporation is excessive reduce it by some means to avoid
plastic shrinkage cracking. Cover the concrete with wet burlap
or polyethylene sheets in between finishing operations if
conditions are severe.
-
Curing
Start curing as
soon as possible. Spray the surface with liquid membrane curing
compound or cover it with damp burlap and keep it moist for at
least 3 days. A second application of curing compound the next
day is a good quality assurance step.
-
Joints
Provisions
for contraction or expansion movements due to temperature and/or
moisture change should be provided with construction of control
joints by sawing, forming or tooling a groove about 1/4 the
thickness of the slab, no further apart than 30 times the
thickness. Often closer spacing of control joints will be
necessary to avoid long thin areas. The length of an area should
not exceed about 1.5 times the width. Isolation joints should be
provided whenever restriction to freedom of either vertical or
horizontal movement is anticipated: such as where floors meet
walls, columns, or footings. These are full-depth joints and are
constructed by inserting a barrier of some type to prevent bond
between the slab and the other elements.
-
Cover Over
Reinforcement
Cracks in
reinforced concrete caused by expansion of rust on reinforcing
steel should be prevented by providing sufficient concrete cover
(at least 2 inches) to keep salt arid moisture from contacting
the steel.
[back]
CRACKING
CRACKS IN BASEMENTS WALLS
-
Temperature and
drying shrinkage cracks.
With few
exceptions, newly placed concrete has Cast-in-place concrete
basements provide durable, high quality extra living space. At
times when proper construction practices are not used
undesirable cracks occur, such as: the largest volume that it
will ever have. This shrinkage tendency is increased by drying
and/or a drop in temperature and can lead to random cracking if
steps are not taken to control the location of the cracks by
providing control joints.
-
Settlement
cracks.
These occur
from non-uniform support of footings or occasionally from
expansive soils.
-
Other structural
cracks.
In basements
these cracks generally occur during backfilling, particularly
when heavy equipment gets too close to the walls.
-
Cracks due to lack
of joints or improper jointing practices.
-
In concrete
basement walls some cracking is normal.
Most cracks normally occur because one or more of the following
rules of "good concrete practice" were not followed:
-
Providing uniform
soil support.
-
Using moderate
slump concrete and avoiding addition of water to the concrete
mixture on the job.
-
Observing proper
concrete placement practices.
-
Providing control
joints every 20 to 30 feet. e. Backfilling carefully and, if
possible, waiting until the first floor is in place in cold
weather. (Concrete gains strength at a slower rate in cold
weather.)
Since the performance of concrete basements is affected by
climate conditions, unusual loads, materials quality and
workmanship, care should always be exercised in their design and
construction. The following steps should be followed:
-
Site conditions
and excavation.
Soil
investigation should be thorough enough to insure design and
construction of foundations suited to the building site. The
excavation should be to the level of the bottom of the footing.
The soil or granular fill beneath the entire area of the
basement should be well compacted by rolling, vibrating or
tamping. Footings must bear on undisturbed soil.
-
Formwork and
reinforcement.
All
form-work must be constructed and braced so that it can
withstand the pressure of the concrete. Reinforcement is
effective in controlling shrinkage cracks and is especially
beneficial where uneven side pressures against the walls may be
expected. Observe state and local guidelines for wall thickness
and reinforcement if needed.
-
Joints.
Shrinkage
and temperature cracking of basement walls can be controlled by
means of properly located and formed joints. As a rule of thumb,
in 8 ft. high and 8 inch thick walls, vertical control joints
should be provided at a spacing of about 30 times the wall
thickness. These wait joints can be formed by nailing a 3/4 inch
thick strip of wood, beveled from 3/4 to 1/2 inch in width, to
the inside of both interior and exterior wall forms. After the
removal, the grooves should be caulked with a good quality joint
filler.
-
Concrete.
In general,
use concrete with a moderate slump (up to 5 inches). Avoid
retempering. Concrete with a higher slump may be used providing
the mixture is specifically designed to produce the required
strength without excessive bleeding and/or segregation. In areas
where weathering is severe and where the walls may be exposed to
moisture and freezing temperatures air entrained concrete should
be used.
-
Placement and
curing.
Place
concrete in a continuous operation to avoid cold joints. If
concrete tends to bleed and segregate slump must be reduced and
the concrete placed in the form every 20 or 30 feet around the
perimeter of the wall. Higher slump concretes that do not bleed
or segregate will flow horizontally for long distances and
reduce the number of required points of access to the form.
Provide adequate curing and protection to fresh concrete. It
should not be allowed to freeze in cold weather. Preventive
measures could be taken by completely enclosing the structure
with polyethylene sheets and, if necessary, providing heat.
-
Waterproofing
and drainage.
Spray or
paint the exterior of walls with damp proofing asphal-tic
compound. Provide foundation drainage by installing drain tiles
or plastic pipes around the exterior of the footing, then
covering with clean granular fill to a height of at least 1 foot
prior to backfill. Water should be drained to lower elevations
suitable to receive storm water run off.
-
Backfilling and
final grading.
Backfilling should
be done carefully to avoid damaging the walls. Brace the walls
or, if possible, have first floor in place before backfill. To
drain the surface water away from the basement finish grade
should fall off 1/2 to 1 inch per foot for at least 8 feet to 10
feet away from the foundation.
[back]
CRAZING
Crazing cracks are small enclosed hairline like cracks less than
1/8 inch deep and usually 3/8 inch to 1 ½ inch across. It is
caused by surface shrinkage stresses as the concrete dries out.
These cracks usually do not affect the durability or wear of the
concrete.
CAUSES:
-
Placing a high slump (wet) concrete.
-
Finishing bleed water back into the slab.
-
Overusing a vibratory screed.
-
Adding a dry shake or cement to the surface.
-
Using un-vented heaters in a building and allowing carbon
monoxide or carbon dioxide to react with the cement
-
Not
curing the slab.
[back]
CURLING
Slabs
on grade do not shrink uniformly from top to bottom. The top
dries out more rapidly than the bottom and tends to shrink more,
and thus every vertical segment of the slab becomes slightly
wedge-shaped.
The
shrinking of concrete when it dries amounts about 1/8th inch in
20 feet. It becomes shorter at the top than on bottom and tends
to dish upwards. Curling induces tensile stresses in the top
part and if these stresses exceed the tensile strength of the
concrete, cracks will appear.
[back]
DELAMINATION OF TROWELED CONCRETE SURFACES
What are Delaminations?
In a delaminated
surface, the top 1/8 inch is densified and separated from the
base slab by a thin layer of air or water. The delaminations on
the surface of a slab may range in size from several square
inches to many square feet and can be detected by a hollow sound
when tapped with a hammer or with a heavy chain drag. They may
exhibit cracking and color differences because of rapid drying
of the thin surface during curing. Traffic or freezing may break
away the surface in large sheets. They are similar to blisters,
but much larger.
Delaminations form during final troweling. They are most
frequent in early spring and late fall when concrete is placed
on a cool sub-grade with rising daytime temperatures, but they
can occur anytime.
Why Does Delamination Occur?
Delamination
occurs when the fresh concrete surface is sealed by troweling
while the underlying concrete is plastic and bleeding or able to
release air. Delaminations form fairly late in the finishing
process after floating and after the first troweling. Rapid
evaporation of bleed water due to surface drying (wind, sun, or
low humidity) makes the surface appear ready to trowel while the
underlying concrete is plastic and can still bleed or release
air. Vapor barriers under slabs force water to rise and compound
the problem. The use of fly ash and chemical retarders will
delay initial set of the underlying concrete and allow bleed
water and air to move upward after the surface is sealed.
Entrained air reduces bleeding and promotes early finishing
which will produce a dense impermeable surface layer. A cool
sub-grade delays set in the bottom relative to the top. Air and
water collect under the dense surface layer during finishing.
Delamination is more likely to form if:
-
The
underlying concrete sets slowly because of a cool subgrade.
-
Set is retarded by retarders and/or fly ash.
-
Entrained air is used (or is higher than normal).
-
Use of a jitterbug or vibrating screed brings too much mortar
to the surface.
-
A
dry shake is used, particularly with air-entrained concrete.
-
The concrete is sticky from higher cementitious material or
sand content.
-
The slab is thick.
-
The slab is placed directly on a vapor barrier.
How to Prevent Delamination:
Be wary of a
concrete surface that appears to be ready to trowel before it
would normally be expected. Emphasis in finishing should be on
screeding, straight-edging, and floating the concrete as rapidly
as possible-without working up an excessive layer of mortar.
Further finishing should be delayed as long as possible, and the
surface covered with polyethylene or otherwise protected from
evaporation. In initial floating, the float blades should be
flat to avoid densifying the surface too early. Accelerators or
heated concrete often prevent delamination in cool weather.
Delamination may be difficult to detect during finishing
operations. If delamination is observed, try to flatten the
trowel blades or tear the surface with a wood float and delay
finishing as long as possible. Any steps that can be taken to
slow evaporation should help.
If a
vapor barrier is required, place a layer of damp fine aggregate
over the plastic sheet. Do not place concrete directly on a
vapor barrier. Do not use air-entrained concrete in floor slabs
which have a hard trowel surface and which will not be subject
to deicing salts.
[back]
DISCOLORATION
Discoloration of concrete are blotches or color changes in the
concrete finish caused by mix change or by efflorencence.
CAUSES
Discoloration
can be caused by changes in cement or fine aggregate but usually
is caused by the inconsistent use of a admixtures, insufficient
mixing time, and improper timing of finishing operations. A
yellowish or greenish hue may appear on the concrete containing
ground slag as a cementitious material. This will disappear in
time. The discoloration of concrete in slabs on grade is usually
the result of a change in either the concrete composition or a
concrete construction practice. In most studies, no single
factor seemed to cause discoloration.
Factors found to influence discoloration are the use of calcium
chloride, variation in cement alkali content, delayed hydration
of the cement paste, admixtures, hard-troweled surfaces or
improper curing or finishing procedures that cause surface
variation of the water-cement ratio, and changes in the concrete
mix.
PREVENTION:
-
Minimize the use of
high-alkali content cements.
-
Calcium chloride is
the primary cause of concrete discoloration.
-
The type, kind, and
condition of formwork can influence the surface color. Forms
with different rates of absorption will cause the surface with
different shades of color. A change in the type or brand of a
form release agent can also change concrete color.
-
Eliminate trowel
burning of the concrete. The most common consequence is that
metal fragments from the trowel are embedded in the surface of
the concrete. Also concrete that has been hand-troweled ,ay have
dark discoloration as a result of densifying the surface, which
reduces the water-cement ratio. The resulting low water-cement
ratio affects the hydration of the cement ferrites which
contributes to a darker color. Concrete surfaces that are
troweled too early will increase the water-cement ratio at the
surface and lighten the color.
-
Concrete which is
not properly or uniformly cured may develop discoloration.
Uneven curing will affect the degree of hydration of the cement.
Curing with polyethylene may also cause discoloration causing
streaks.
-
The discoloration
of a slab may be minimized or prevented by moistening the
absorptive sub-grades, following proper curing procedures. And
adding proper protection of the concrete from drying by the wind
and sun.
[back]
DUSTING
When
the surface of the concrete develops a powered or chalk like
material it is referred to as dusting. A weak surface is to
blame for chalking and will keep appearing as traffic wares away
the surface.
CAUSES:
-
Finishing bleed water back into the surface of the slab.
-
Not
curing the slab which can result in a soft surface.
-
Carbon dioxide or carbon monoxide fumes having a reaction with
the cement.
-
Rain or condensation being finished back into the slab. Anytime
water is worked back into the surface it increased the
water-cement ratio and weakens the surface layer.
[back]
SCALING
Scaling is when the surface of a hardened concrete slab breaks
away from the slab to a depth of about 1/16 to 1/4 in. This
usually occurs at an early age.
Concrete placed in late fall will be susceptible to scaling
during the first winter if proper procedures are not followed.
Fly ash in concrete has been regarded by some as a potential
risk to scaling. Fly ash should not, however be of concern if
the levels of air content and strength achieved are comparable
to those required for concrete that contains no fly ash.
The
use of entrained air will do a great deal to eliminate scaling,
but it cannot be considered an absolute cure-all, particularly
for saturated concrete exposed to deicing salts early in its
life. Concretes placed in the spring and early summer generally
perform more satisfactorily than those placed in the fall or
winter because they have had an opportunity to gain strength and
finally dry out before freezing weather.
PROPER FINISHING:
The necessity of
using proper finishing techniques cannot be overemphasized. No
finishing operations should ever proceed when bleed water is
present on the surface of the concrete. Finishing in the
presence of bleed water produces a high water-cement ratio and
very low strength in the top 1/8 to ¼ inch of the surface. The
use of moderate-slump concrete (3-5 in.) is recommended.
CAUSES:
-
Early cycles of freezing and thawing of the surface of newly
placed concrete.
-
Applications of deicers the first year.
-
Any finishing operation performed while bleed water is on the
surface, will cause scaling. Mixing excess water into the top of
the slab will cause a segregation of the surface fines (sand and
cement) and cause scaling.
PREVENTION:
-
The
temperature of freshly placed concrete should be maintained
above 50F for at least 5 days when using a normal mix.
-
Use air-entrained concrete
-
No
finishing operation should ever be preformed while bleed water
is present. Remove bleed water by dragging a rubber garden hose
over the surface.
[back]
SHRINKING
PLASTIC SHRINKAGE CRACKS:
Cracks that
appear on the surface of freshly placed concrete during
finishing or soon after. Rapid loss of moisture from fresh
concrete often leads to cracking (surface water evaporates at a
faster rate that it can replaced by bleed water). Although
plastic cracks are unsightly they rarely impair the strength of
the concrete.
CAUSES:
The cause of
plastic cracking is one or a combination of the following:
-
Wind and low humidity (if relative humidity changes from 90% to
50% the rate of evaporation is increased 5 times).
-
Exposure to the sun
-
High ambient temperature ( when the temperature increases from
50F to 70F the rate of evaporation of water from the surface
doubles).
-
High concrete temperature (rapid evaporation and cracking may
occur when the temperature of concrete is significantly higher
than the air temperature).
-
Dry
sub-grade
PREVENTION:
-
If
no vapor barrier is used, the sub-grade should be saturated just
before placing the concrete.
-
Have plenty of help and finish promptly. If delays occur, cover
with wet burlap or polyethylene sheeting.
-
Cure as soon as possible
[back]
|